1. Before installing the Precision Linear Shaft, the burrs, dirt and surface scars on the mechanical installation surface must be removed. The Precision Linear Shaft is coated with anti-rust oil. Before installation, please clean the reference surface with cleaning oil before installation. Usually, the reference surface is easy to rust after removing the anti-rust oil. It is recommended to coat the spindle with low viscosity with lubricating oil.

2. Gently place the Precision Linear Shaft on the bed platform, and use the side fixing screws or other fixing fixtures to make the line rail and the side installation surface fit gently. Before installation and use, it is necessary to confirm whether the screw holes match. If the machined holes of the base do not match and the bolts are forcibly locked, it will greatly affect the combination accuracy and use quality.

3. Tighten the positioning screws of the linear bearing in order from the center to both sides, so that the track fits the vertical mounting surface, and tighten from the center to both ends to obtain a more stable accuracy. After the vertical datum surface is slightly tightened, the locking force of the lateral datum surface is strengthened, so that the linear bearing can effectively fit the lateral datum surface.

4. Use a torque wrench to tighten the torque one by one according to various materials, and slowly tighten the positioning screws of the linear bearing slide rail.

5. Use the same installation method to install the auxiliary rails, and individually install the sliding seats to the main rails and auxiliary rails.

Note that after the sliding seat is installed on the linear slide rail, many subsequent accessories cannot be installed due to the limited installation space, and the required accessories must be installed together at this stage.

6. Gently place the mobile platform on the sliding seat of the main rail and auxiliary rail of the linear bearing, and then lock the lateral tightening screws on the mobile platform, and the installation and positioning can be completed.